BIM QA/QC Dashboard

LON-001 · Canary Wharf Data Centre
Stage 4 · Technical Design Data as of 26 Sep 2026 Sample data

Overall Compliance

Combined score across automated model QA/QC, Level of Information, Level of Detail and MIDP delivery for every federated discipline model. Target for Stage 4 sign-off is 90%.

QA/QC Compliance by Model

Automated rule checks run against each discipline model on upload to ACC: ISO 19650 naming, shared coordinates, Uniclass classification, parameter completeness, model health, worksets/links and sheet setup.

Model check register

Latest check result per model · 156 rules per model

Level of Information (LOI)

Share of required parameters populated on modelled elements, measured against the Stage 4 information requirements (EIR / AIR, COBie-aligned).

Lowest-scoring attributes

Required parameters with the most missing values

Level of Detail (LOD)

Geometric development of modelled elements. At Stage 4 every element is expected to reach LOD 350 or above.

Element categories below target

Largest groups still under LOD 350

MIDP Compliance

Delivery of information containers against the Master Information Delivery Plan. A deliverable is compliant when issued to Shared on or before its planned date.

Deliverables needing attention

Overdue, late and due in the next 14 days

Clash Detection

Results of the weekly federated clash run (hard clashes, 25 mm tolerance) across all discipline models.

Clash tests

Latest run · 26 Sep 2026

Design Review · ACC Issues

Design review comments raised as issues in Autodesk Construction Cloud for the Stage 4 review cycle.

Open issues

Sorted by days open

Stakeholder Involvement

ACC project activity over the last 30 days: model and document uploads, issues raised and closed, and review actions, by person, team and company.

Project members

Activity in the last 30 days

Recent activity

Latest ACC events

    Demonstration build — all projects, models, people and companies shown are sample data.